Prepare a separation system installation with verified lifting points, foundation loads, alignment, utility connections and a documented commissioning plan.

Illustrative SENZ industrial separation equipment. Configuration and suitability must be confirmed for the proposed duty.
Confirm the installation documents before delivery
Obtain the general arrangement, foundation and load information, lifting instructions, center of gravity, service clearances and utility requirements for the supplied configuration. An equipment package can include items with very different handling requirements. Assign responsibilities for unloading, lifting, foundations, electrical work, piping and commissioning, and agree how discrepancies will be recorded.
Receive and lift equipment correctly
Inspect shipment condition and reconcile the packing list before assembly. Use the specified lifting points and rated lifting equipment under a competent lifting plan. Motor eyes, pipe nozzles, guards and handrails are not automatically lifting points for an entire skid. Keep transport restraints in place or remove them only as the instructions require. Protect machined surfaces and openings during storage.
Avoid forcing the system into alignment
Check foundation level, anchors, access and vibration-control arrangements against the drawings. Align drives and connected components using their procedures. Support piping independently so it does not impose unintended loads on pump or separator connections. Flush construction debris from the appropriate piping circuits before connection or startup, using a method compatible with the equipment and process.
Commission in controlled stages
Qualified personnel should complete electrical and protective-function checks. Verify instruments, motor direction using the approved procedure, pump readiness, dosing delivery and conveyor discharge. Follow the specified dry, water or process trial sequence; not every component may run dry. Record settings, alarms, interlocks, leakage, vibration and agreed performance tests before accepting the system.
Practical assessment checklist
| Check | What to confirm |
|---|---|
| Lifting | Weights, center of gravity and approved lifting arrangement |
| Foundation | Static/dynamic loads, anchors, level and access |
| Connections | Utilities, pipe supports and electrical protection |
| Acceptance | Completed inspections, operating test and training |
Frequently asked questions
Can a skid be lifted by any visible eye bolt?
No. Use the lifting arrangement specified for the complete load. Component lifting points may support only that component.
Can piping be pulled into place using the equipment flange?
Avoid imposing unintended loads. Correct piping support and alignment before completing the connection.
What should be handed over after commissioning?
As-built drawings, manuals, settings, test records, spare-parts information, training and the agreed punch-list status.
Related reading
- Maintenance for a Complete Separation Equipment System
- Are there different types of complete sets of equipment?
Discuss your process with SENZ
For industrial separation equipment, send the feed composition, flow rate, operating conditions and required outlet quality. Contact SENZ to review the application, test requirements and scope of supply.






